Last May, the water treatment plant for Tan Hoi IP was handed over to the customer. Commenced in 12/2014, the construction and installation phase were then finished in 07/2015. In 08/2015, the plant started to produce the first batches of clean water.
Tan Hoi IP’s water treatment plant is capable of supplying 3,000 m3 of clean water per day. The water quality meets the National Standard QCVN 02:2009/BYT.
Some photos of the treatment plant after hand-over: